<?xml version="1.0" encoding="UTF-8" standalone="yes"?>
<Project xmlns="http://schemas.microsoft.com/project">
    <SaveVersion>14</SaveVersion>
    <Name>Line 3 Packaging Line Installation (sample)</Name>
    <Title>Line 3 Packaging Line Installation (sample)</Title>
    <ScheduleFromStart>1</ScheduleFromStart>
    <StartDate>2027-03-01T08:00:00</StartDate>
    <FinishDate>2027-06-17T08:00:00</FinishDate>
    <FYStartDate>1</FYStartDate>
    <CriticalSlackLimit>0</CriticalSlackLimit>
    <CurrencyDigits>2</CurrencyDigits>
    <CurrencySymbol>$</CurrencySymbol>
    <CurrencySymbolPosition>0</CurrencySymbolPosition>
    <CalendarUID>1</CalendarUID>
    <DefaultStartTime>08:00:00</DefaultStartTime>
    <MinutesPerDay>480</MinutesPerDay>
    <MinutesPerWeek>2400</MinutesPerWeek>
    <DaysPerMonth>20</DaysPerMonth>
    <DefaultTaskType>0</DefaultTaskType>
    <DefaultFixedCostAccrual>2</DefaultFixedCostAccrual>
    <DurationFormat>7</DurationFormat>
    <WorkFormat>2</WorkFormat>
    <EditableActualCosts>0</EditableActualCosts>
    <HonorConstraints>0</HonorConstraints>
    <EarnedValueMethod>0</EarnedValueMethod>
    <InsertedProjectsLikeSummary>0</InsertedProjectsLikeSummary>
    <MultipleCriticalPaths>0</MultipleCriticalPaths>
    <NewTasksEffortDriven>0</NewTasksEffortDriven>
    <NewTasksEstimated>1</NewTasksEstimated>
    <SplitsInProgressTasks>0</SplitsInProgressTasks>
    <SpreadActualCost>0</SpreadActualCost>
    <SpreadPercentComplete>0</SpreadPercentComplete>
    <TaskUpdatesResource>1</TaskUpdatesResource>
    <FiscalYearStart>0</FiscalYearStart>
    <WeekStartDay>1</WeekStartDay>
    <MoveCompletedEndsBack>0</MoveCompletedEndsBack>
    <MoveRemainingStartsBack>0</MoveRemainingStartsBack>
    <MoveRemainingStartsForward>0</MoveRemainingStartsForward>
    <MoveCompletedEndsForward>0</MoveCompletedEndsForward>
    <BaselineForEarnedValue>0</BaselineForEarnedValue>
    <AutoAddNewResourcesAndTasks>1</AutoAddNewResourcesAndTasks>
    <StatusDate>2027-04-12T17:00:00</StatusDate>
    <CurrentDate>2026-11-09T13:05:01</CurrentDate>
    <MicrosoftProjectServerURL>1</MicrosoftProjectServerURL>
    <Autolink>1</Autolink>
    <NewTaskStartDate>0</NewTaskStartDate>
    <NewTasksAreManual>1</NewTasksAreManual>
    <DefaultTaskEVMethod>0</DefaultTaskEVMethod>
    <ProjectExternallyEdited>0</ProjectExternallyEdited>
    <ActualsInSync>0</ActualsInSync>
    <RemoveFileProperties>0</RemoveFileProperties>
    <AdminProject>0</AdminProject>
    <ExtendedAttributes/>
    <Calendars/>
    <Tasks>
        <Task>
            <UID>1</UID>
            <ID>1</ID>
            <Name>Line 3 equipment purchase order</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>1</WBS>
            <OutlineNumber>1</OutlineNumber>
            <OutlineLevel>1</OutlineLevel>
            <Priority>500</Priority>
            <Start>2027-03-01T08:00:00</Start>
            <Finish>2027-03-03T17:00:00</Finish>
            <Duration>PT24H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>0</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <TotalSlack>9600</TotalSlack>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>100</PercentComplete>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <Baseline>
                <Number>0</Number>
                <Start>2027-03-01T08:00:00</Start>
                <Finish>2027-03-03T17:00:00</Finish>
            </Baseline>
        </Task>
        <Task>
            <UID>2</UID>
            <ID>2</ID>
            <Name>Vendor build of filler and capper</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>2</WBS>
            <OutlineNumber>2</OutlineNumber>
            <OutlineLevel>1</OutlineLevel>
            <Priority>500</Priority>
            <Start>2027-03-04T08:00:00</Start>
            <Finish>2027-04-15T17:00:00</Finish>
            <Duration>PT248H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>0</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <TotalSlack>9600</TotalSlack>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>50</PercentComplete>
            <RemainingDuration>PT124H0M0S</RemainingDuration>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes>Vendor reports PLC software rework before FAT.</Notes>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>1</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2027-03-04T08:00:00</Start>
                <Finish>2027-04-07T17:00:00</Finish>
            </Baseline>
        </Task>
        <Task>
            <UID>3</UID>
            <ID>3</ID>
            <Name>Factory acceptance test (FAT) at vendor</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>3</WBS>
            <OutlineNumber>3</OutlineNumber>
            <OutlineLevel>1</OutlineLevel>
            <Priority>500</Priority>
            <Start>2027-04-16T08:00:00</Start>
            <Finish>2027-04-21T17:00:00</Finish>
            <Duration>PT32H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>0</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <TotalSlack>9600</TotalSlack>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>0</PercentComplete>
            <RemainingDuration>PT32H0M0S</RemainingDuration>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>2</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2027-04-08T08:00:00</Start>
                <Finish>2027-04-13T17:00:00</Finish>
            </Baseline>
        </Task>
        <Task>
            <UID>4</UID>
            <ID>4</ID>
            <Name>Shipping and customs</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>4</WBS>
            <OutlineNumber>4</OutlineNumber>
            <OutlineLevel>1</OutlineLevel>
            <Priority>500</Priority>
            <Start>2027-04-22T08:00:00</Start>
            <Finish>2027-05-03T17:00:00</Finish>
            <Duration>PT64H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>0</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <TotalSlack>9600</TotalSlack>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>0</PercentComplete>
            <RemainingDuration>PT64H0M0S</RemainingDuration>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>3</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2027-04-14T08:00:00</Start>
                <Finish>2027-04-23T17:00:00</Finish>
            </Baseline>
        </Task>
        <Task>
            <UID>5</UID>
            <ID>5</ID>
            <Name>Floor preparation and anchor points</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>5</WBS>
            <OutlineNumber>5</OutlineNumber>
            <OutlineLevel>1</OutlineLevel>
            <Priority>500</Priority>
            <Start>2027-03-04T08:00:00</Start>
            <Finish>2027-03-17T17:00:00</Finish>
            <Duration>PT80H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>0</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <TotalSlack>153600</TotalSlack>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>100</PercentComplete>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>1</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2027-03-04T08:00:00</Start>
                <Finish>2027-03-17T17:00:00</Finish>
            </Baseline>
        </Task>
        <Task>
            <UID>6</UID>
            <ID>6</ID>
            <Name>Utility tie-in during plant shutdown</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>6</WBS>
            <OutlineNumber>6</OutlineNumber>
            <OutlineLevel>1</OutlineLevel>
            <Priority>500</Priority>
            <Start>2027-05-03T08:00:00</Start>
            <Finish>2027-05-05T17:00:00</Finish>
            <Duration>PT24H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>0</PercentComplete>
            <RemainingDuration>PT24H0M0S</RemainingDuration>
            <ConstraintType>4</ConstraintType>
            <CalendarUID>-1</CalendarUID>
            <ConstraintDate>2027-05-03T08:00:00</ConstraintDate>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <Notes>Plant shutdown window moved by operations to the week of 3 May.</Notes>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>5</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2027-04-12T08:00:00</Start>
                <Finish>2027-04-14T17:00:00</Finish>
            </Baseline>
        </Task>
        <Task>
            <UID>7</UID>
            <ID>7</ID>
            <Name>Mechanical installation</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>7</WBS>
            <OutlineNumber>7</OutlineNumber>
            <OutlineLevel>1</OutlineLevel>
            <Priority>500</Priority>
            <Start>2027-05-06T08:00:00</Start>
            <Finish>2027-05-19T17:00:00</Finish>
            <Duration>PT80H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>0</PercentComplete>
            <RemainingDuration>PT80H0M0S</RemainingDuration>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>4</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <PredecessorLink>
                <PredecessorUID>6</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2027-04-26T08:00:00</Start>
                <Finish>2027-05-07T17:00:00</Finish>
            </Baseline>
        </Task>
        <Task>
            <UID>8</UID>
            <ID>8</ID>
            <Name>Electrical and control panel installation</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>8</WBS>
            <OutlineNumber>8</OutlineNumber>
            <OutlineLevel>1</OutlineLevel>
            <Priority>500</Priority>
            <Start>2027-05-06T08:00:00</Start>
            <Finish>2027-05-17T17:00:00</Finish>
            <Duration>PT64H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>0</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <TotalSlack>9600</TotalSlack>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>0</PercentComplete>
            <RemainingDuration>PT64H0M0S</RemainingDuration>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>4</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <PredecessorLink>
                <PredecessorUID>6</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2027-04-26T08:00:00</Start>
                <Finish>2027-05-05T17:00:00</Finish>
            </Baseline>
        </Task>
        <Task>
            <UID>9</UID>
            <ID>9</ID>
            <Name>PLC and MES integration</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>9</WBS>
            <OutlineNumber>9</OutlineNumber>
            <OutlineLevel>1</OutlineLevel>
            <Priority>500</Priority>
            <Start>2027-05-20T08:00:00</Start>
            <Finish>2027-05-27T17:00:00</Finish>
            <Duration>PT48H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>0</PercentComplete>
            <RemainingDuration>PT48H0M0S</RemainingDuration>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>7</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <PredecessorLink>
                <PredecessorUID>8</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2027-05-10T08:00:00</Start>
                <Finish>2027-05-17T17:00:00</Finish>
            </Baseline>
        </Task>
        <Task>
            <UID>10</UID>
            <ID>10</ID>
            <Name>Site acceptance test (SAT)</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>10</WBS>
            <OutlineNumber>10</OutlineNumber>
            <OutlineLevel>1</OutlineLevel>
            <Priority>500</Priority>
            <Start>2027-05-28T08:00:00</Start>
            <Finish>2027-06-02T17:00:00</Finish>
            <Duration>PT32H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>0</PercentComplete>
            <RemainingDuration>PT32H0M0S</RemainingDuration>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>9</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2027-05-18T08:00:00</Start>
                <Finish>2027-05-21T17:00:00</Finish>
            </Baseline>
        </Task>
        <Task>
            <UID>11</UID>
            <ID>11</ID>
            <Name>Operational qualification (OQ)</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>11</WBS>
            <OutlineNumber>11</OutlineNumber>
            <OutlineLevel>1</OutlineLevel>
            <Priority>500</Priority>
            <Start>2027-06-03T08:00:00</Start>
            <Finish>2027-06-09T17:00:00</Finish>
            <Duration>PT40H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>0</PercentComplete>
            <RemainingDuration>PT40H0M0S</RemainingDuration>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>10</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2027-05-24T08:00:00</Start>
                <Finish>2027-05-28T17:00:00</Finish>
            </Baseline>
        </Task>
        <Task>
            <UID>12</UID>
            <ID>12</ID>
            <Name>Performance qualification run (PQ)</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>12</WBS>
            <OutlineNumber>12</OutlineNumber>
            <OutlineLevel>1</OutlineLevel>
            <Priority>500</Priority>
            <Start>2027-06-10T08:00:00</Start>
            <Finish>2027-06-16T17:00:00</Finish>
            <Duration>PT40H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>0</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>0</PercentComplete>
            <RemainingDuration>PT40H0M0S</RemainingDuration>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>11</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2027-05-31T08:00:00</Start>
                <Finish>2027-06-04T17:00:00</Finish>
            </Baseline>
        </Task>
        <Task>
            <UID>13</UID>
            <ID>13</ID>
            <Name>Release to production</Name>
            <Active>1</Active>
            <Manual>0</Manual>
            <Type>0</Type>
            <IsNull>0</IsNull>
            <WBS>13</WBS>
            <OutlineNumber>13</OutlineNumber>
            <OutlineLevel>1</OutlineLevel>
            <Priority>500</Priority>
            <Start>2027-06-17T08:00:00</Start>
            <Finish>2027-06-17T08:00:00</Finish>
            <Duration>PT0H0M0S</Duration>
            <DurationFormat>7</DurationFormat>
            <ResumeValid>0</ResumeValid>
            <EffortDriven>0</EffortDriven>
            <Recurring>0</Recurring>
            <OverAllocated>0</OverAllocated>
            <Estimated>0</Estimated>
            <Milestone>1</Milestone>
            <Summary>0</Summary>
            <Critical>1</Critical>
            <IsSubproject>0</IsSubproject>
            <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
            <ExternalTask>0</ExternalTask>
            <FixedCostAccrual>3</FixedCostAccrual>
            <PercentComplete>0</PercentComplete>
            <CalendarUID>-1</CalendarUID>
            <LevelAssignments>0</LevelAssignments>
            <LevelingCanSplit>0</LevelingCanSplit>
            <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
            <HideBar>0</HideBar>
            <Rollup>0</Rollup>
            <EarnedValueMethod>0</EarnedValueMethod>
            <PredecessorLink>
                <PredecessorUID>12</PredecessorUID>
                <Type>1</Type>
                <CrossProject>0</CrossProject>
                <LinkLag>0</LinkLag>
                <LagFormat>7</LagFormat>
            </PredecessorLink>
            <Baseline>
                <Number>0</Number>
                <Start>2027-06-07T08:00:00</Start>
                <Finish>2027-06-07T08:00:00</Finish>
            </Baseline>
        </Task>
    </Tasks>
    <Resources/>
    <Assignments>
        <Assignment>
            <UID>1</UID>
            <TaskUID>1</TaskUID>
            <ResourceUID>-65535</ResourceUID>
            <PercentWorkComplete>100</PercentWorkComplete>
            <ActualWork>PT24H0M0S</ActualWork>
            <Finish>2027-03-03T17:00:00</Finish>
            <HasFixedRateUnits>1</HasFixedRateUnits>
            <FixedMaterial>0</FixedMaterial>
            <LevelingDelayFormat>7</LevelingDelayFormat>
            <Start>2027-03-01T08:00:00</Start>
            <Units>1</Units>
            <Work>PT24H0M0S</Work>
        </Assignment>
        <Assignment>
            <UID>2</UID>
            <TaskUID>2</TaskUID>
            <ResourceUID>-65535</ResourceUID>
            <PercentWorkComplete>50</PercentWorkComplete>
            <ActualWork>PT124H0M0S</ActualWork>
            <Finish>2027-04-15T17:00:00</Finish>
            <HasFixedRateUnits>1</HasFixedRateUnits>
            <FixedMaterial>0</FixedMaterial>
            <LevelingDelayFormat>7</LevelingDelayFormat>
            <RemainingWork>PT124H0M0S</RemainingWork>
            <Start>2027-03-04T08:00:00</Start>
            <Units>1</Units>
            <Work>PT248H0M0S</Work>
        </Assignment>
        <Assignment>
            <UID>3</UID>
            <TaskUID>5</TaskUID>
            <ResourceUID>-65535</ResourceUID>
            <PercentWorkComplete>100</PercentWorkComplete>
            <ActualWork>PT80H0M0S</ActualWork>
            <Finish>2027-03-17T17:00:00</Finish>
            <HasFixedRateUnits>1</HasFixedRateUnits>
            <FixedMaterial>0</FixedMaterial>
            <LevelingDelayFormat>7</LevelingDelayFormat>
            <Start>2027-03-04T08:00:00</Start>
            <Units>1</Units>
            <Work>PT80H0M0S</Work>
        </Assignment>
    </Assignments>
</Project>